Assembly 303 Continuous
Footings with Piers
Situation and Assumptions:
This assembly will takeoff continuous footings with
intermittent pier footings. All quantity calculations of the footings and piers
occur separately. The forming, keyway, waterstop, and rebar will be taken off for
both structures. Indicate the concrete psi and the method of concrete
placement. Review the variable windows carefully for the options available.
The forming and keyway are taken off automatically for the dimensions. For
waterstop, input the proper waterstop code. Review the variable window for
options. Answer YES to Takeoff Rebar? if you wish to takeoff rebar with the
concrete. Additional rebar variables will appear. Rebar is available from #3
to #14 bar. For earthwork, answer YES at the Takeoff Earthwork? question. The
earthwork variables will prompt the user for the additional information required.
For backfill calculations, a wall 1 foot thick is assumed for the excavation depth minus
the footing height. Review the variable notes carefully for the excavation methods
and backfill material.
Note: Piers & Footing calculated separately
. |